Rural Electrification

The balance of Global Rural Electrification Program (GREP) achievements to October 2015, is as follows:

  • The electrification by connection to networks 39 015 villages that allowed the access to electricity in 2085 273 households (over 12,5 million inhabitants);
  • The rural electrification rate reached 99,13%;
  • The total investment budget is approximately realized 22,4 billion DH;
  • The equipment of 51,559 homes by individual photovoltaic kits in 3663 villages;

The yearly evolution of these cumulative achievements is as follows:

  1. In terms of cumulative villages:

    DE-A

  2. In terms of cumulative homes:

    DE-B

  • Evolution of the rural electrification rate:

    The evolution of the RER in 1995 is as follows:

    DE-ER-1

  • Cumulative GREP achievements investment (in MDH):

    At the end of October 2015, total investments made GREP are 22, 4 billion dirhams. The accumulation of these investments since 1996 is distributed as follows:

    DE-ER-2

  • GREP financing:

    With an overall budget at the end of 2017, of around 24 billion dirhams, GREP has seen strong participation of donors who contributed in financing this project with an amount of 12, 25 billion dirhams representing and 51,4% of the total budget.


  • GREP action plan 2015 - 2017:

    The action plan of the GREP during the period 2015 - 2017, regarding the electrification of 2 437 villages involving 69 718 homes by the network interconnected.
    This period also will know the electrification of 3 900 schools, 170 clinics and 1550 mosques.